Planning and status of the project

Timetable of the NFI

  • 2000 needs analysis NFI3, evaluation of the NFI2-attributes
  • 2001 needs analysis NFI3, impact analysis NFI1/NFI2, data catalog NFI3, development of inventory methods, database development
  • 2002 programming of field computers, preliminary inventory NFI3
  • 2003 analysis of the preliminary inventory, start of the aerial photo interpretation, recruitment of field workers
  • 2004 field survey NFI3
  • 2005 field survey NFI3, software development for data analysis of the field survey NFI3
  • 2006 field survey NFI3, data analysis concept for the field survey LFI3
  • 2007 data analysis
  • 2008 NFI3-results in manuscript form
  • 2009 field survey NFI4
  • 2010 field survey NFI4, publication of the main results NFI3

date of acquisition of NFI-data

schedule of aerial photos schedule of terrestrial inventory
NFI4 map schedule N/A
NFI3 map schedule map field survey
NFI2 map schedule map field survey
NFI1 map schedule map field survey